A flat handover checklist has 2 halves: a room-by-room snag list and a set of papers. Walk every room with a tape, a spirit level and a torch. Log each defect with a photo. Then collect 8 key papers, led by the occupancy certificate. Under Section 14(3) of the RERA Act, 2016, the builder must fix defects you report within 5 years, in 30 days each.
1. Your rights at handover under the RERA Act
Know the law before you walk in. Four sections of the RERA Act, 2016 shape handover day.
| Section | What it says | What it means for you |
|---|---|---|
| 19(10) | Take physical possession within 2 months of the OC | Plan your move once the OC arrives |
| 14(3) | Builder fixes defects you report within 5 years of possession, within 30 days, free | Your snag rights do not end at handover |
| 17 | Conveyance deed within 3 months of the OC, where no local law sets a time | Push for the registered deed on time |
| 11(4)(d) | Builder runs essential services at fair charges until the owners’ association takes over | Ask who manages the site in year 1 |
The 5-year window is your safety net. But the first walk-through still matters most. A defect you log on day 1 is hard for anyone to dispute.
For how RERA tracks a project before handover, see our Telangana RERA check guide. For the Vantage dates, read our possession guide.
2. What to bring on inspection day
Book a 3 to 4 hour slot in daylight. Large homes take time. A 6,546 sq ft 4 BHK has many more points to test than a 2 BHK.
Bring these 10 items:
- A 5 m measuring tape
- A spirit level, or a level app on your phone
- A torch for ducts and corners
- A phone charger to test each socket
- A small ball or marble to test floor slope
- A bucket for a water test on balconies
- Masking tape to mark defects on the wall
- The unit plan and the specifications sheet
- A notebook, with rooms listed in order
- A friend to note while you test
Take a photo of each defect with the masking tape mark in view. Name each photo by room and number, such as “Kitchen-04”. A list of 40 named photos is far easier to track than 40 loose ones.
3. The snag list, room by room
Go room by room in 1 fixed order. Start at the main door and end at the balconies. In each of the 10 areas below, test each item, then tick it or log it.
| Room | What to check | How to test |
|---|---|---|
| Main and service doors | Frame, lock, hinges, gap at the floor | Open and shut 5 times; check the latch |
| Living and dining | Wall finish, ceiling, skirting, switches | Shine a torch along walls for waves and cracks |
| Kitchen | Hob and chimney points, sink, taps, slope to drain | Run water 2 minutes; check under the sink |
| Bedrooms | Wardrobe space, windows, sockets, AC points | Test every socket with a charger |
| Bathrooms | Slope to drain, taps, flush, grout, leaks | Fill the floor with water; watch where it goes |
| Balconies | Railing height and fix, slope, drain | Pour a bucket of water; check for pooling |
| Windows | Frames, glass, handles, seals | Close and look for light gaps at the edges |
| Floors | Hollow tiles, chips, level | Tap tiles with a coin; roll a ball |
| Electrical | DB labels, MCBs, earthing, meter | Switch each MCB off and on |
| Utility and ducts | Water meter, gas point, drain access | Check for damp near shafts |
The 3 tests that catch the most
First, tap every floor tile with a coin. A hollow sound means a weak bond below, and that tile may crack within 1 or 2 years. Second, flood each bathroom and balcony floor. Water should reach the drain in under 1 minute, with no pools left behind. Third, test every socket in each of the 4 or 5 bedrooms with a phone charger.
Walls, ceilings and paint
Hold a torch flat against each wall. Light at a low angle shows waves, patches and fine cracks. Hairline cracks under 1 mm are common in new plaster, but log them anyway. Check the ceiling above each bathroom for damp spots, since that points to a leak from the floor above.
Doors and windows
Open and close each door 5 times. It should swing freely and latch at the first push. Check the gap at the floor, which should be even along its full width. For the 2 Vantage entries, test both the main door and the service door.
On each window, slide the panel from end to end. Look for light at the edges once it is shut. On a high floor in the Kokapet–Narsingi belt, wind can push rain through a poor seal. So pour a cup of water along the outer track and watch the inner sill.
Plumbing and wet areas
Run every tap for 2 minutes, hot and cold. Look under each sink for drips. Flush each toilet 3 times and listen for a running cistern. Check that the floor trap has a grille and that no smell comes up from it.
Electrical and meters
Open the distribution board and check that each of the MCBs has a label. Switch them off and on, one at a time, and note which room goes dark. A 6,546 sq ft home has many circuits, so a clear label saves hours later. Test each AC point and geyser point too, since those carry the heaviest loads in a Hyderabad summer. Ask for an earthing test report, and check that the meter shows your unit number.
Balconies and railings
Vantage balconies run all around the home, 5 ft to 12 ft 6 in deep. Push firmly on each railing at 3 or 4 points. It should not flex. Pour a bucket of water on each deck and watch it run to the drain. Standing water after 10 minutes means the slope is wrong.
Check the sill where each deck meets the room. Water should not creep under the door frame. On the double-height decks, look up at the ceiling for stains from the floor above.
4. Checks linked to Vantage specifications## 4. Checks linked to Vantage specifications
For a Sri Aditya Vantage home, match the snag list to the brochure specifications. Our specifications guide explains each of the 9 items below.
| Spec in the brochure | What to check at handover |
|---|---|
| Aluminium windows, provision for mosquito mesh | Smooth slide, tight seal, mesh tracks in place |
| Kitchen: hob and chimney points, modular kitchen provision | Points where the plan shows them; gas line capped |
| 3-phase power, pre-paid meters | Meter live, balance shown, 3 phases in the DB |
| 100% DG backup with AMF panel | Ask for a live power-cut test |
| Water softening plant, meter per home | Meter reads; soft water at the taps |
| Central gas bank, pre-paid meters | Gas meter fitted and sealed |
| Intercom and panic button in lifts | Press both and confirm a reply |
| NBC fire hydrants, sprinklers, alarms | Sprinkler heads clean and uncovered |
| Balconies 5 ft to 12 ft 6 in deep | Depth matches the plan; railing fixed |
The brochure lists a provision for a modular kitchen, not a fitted one. So do not log a missing kitchen as a snag. Log only the points and lines the Vantage specs promise.
Also check your area against the agreement. Carpet at Vantage is about 75% of saleable. Measure the rooms and compare with the carpet area in your agreement. Our carpet vs super built-up guide shows how.
5. The 8 papers to collect
The snag list protects the home. The papers protect your title. Collect all 8 before or on the day you sign the possession letter.
| # | Document | Why it matters |
|---|---|---|
| 1 | Occupancy certificate (OC) | The local body has cleared the building to live in |
| 2 | Possession letter | Fixes your possession date, which starts the 5-year defect window |
| 3 | Paid-up receipts and no-dues letter | Proof you owe nothing more |
| 4 | Registered sale or conveyance deed | Your title; stamp duty paid at registration |
| 5 | Allotted parking letter | Bay number in writing |
| 6 | Warranty cards and manuals | Fittings, fixtures and any appliances |
| 7 | As-built plan of your unit | Shows ducts, wiring and pipe runs |
| 8 | Society and maintenance papers | Rules, rates, corpus receipt |
Do not accept possession without the OC. Without it, the home is not cleared to live in, and banks may hold back the last loan payment. Our documents checklist covers the full title set for Hyderabad.
You pay stamp duty when you register the deed. In Telangana, stamp, transfer and registration total 7.5%. Our stamp duty guide has worked examples. If you have a loan, the bank will want the original deed too. See our home loan guide for how the last of the 3 or 4 payouts works.
6. How to log snags and get them fixed
A list only helps if it leads to repairs. Follow these 5 steps.
- Number every snag. Use a sheet with 4 columns: room, item, photo name and date.
- Send it in writing. Send a signed letter or email to Sri Aditya Homes, with photos, and keep a copy.
- Get a fix date. Ask for a date for each of the items, and 1 named person to follow up with.
- Re-inspect. Walk the home a 2nd time once the team says the fixes are done.
- Sign with notes. If items remain on day 2, write them on the possession letter before you sign.
Section 14(3) gives the builder 30 days to fix a defect you report. That clock runs for 5 years from possession. Keep every email. If fixes stall, you can file a complaint with Telangana RERA.
7. Common areas and the society handover
Your home sits inside a larger site. At a project like Vantage, that means 9 towers, a 1,00,000 sq ft club and 3.5 acres of amenities.
Check the common areas you use each day. Test the V3F lifts from the podium to your floor, and press the intercom and panic button in the car. Look at the EV parking floor and your allotted bay. Walk the lobby and the NBC fire exits on your floor. Note any snags in writing, just as you did inside the home.
Section 17 of the RERA Act says the builder must hand the common areas and key plans to the owners’ association. Under Section 11(4)(d), the builder runs the site at fair charges until then. Ask for the date of the first general body meeting. Also ask in which month the corpus fund moves to the association. Our maintenance charges guide explains the corpus and the monthly bill.
8. The handover checklist on one page
Here is the full list in 5 rows.
| Stage | Key checks |
|---|---|
| Before the day | OC issued, RERA dates checked, dues cleared, 3 to 4 hour slot booked |
| Inside the home | 10 rooms and systems, tile tap test, water test, socket test |
| Specs | Windows, kitchen points, meters, backup, gas, fire safety |
| Papers | 8 documents, led by the OC and the possession letter |
| After the day | Snag sheet sent, fix dates set, re-inspection, notes on the letter |
Handover for Vantage is some way off. RERA completion is reported for August 2028. But the checks start at booking. Our site visit checklist covers what to confirm now, and the specifications set the standard you will test against later.
Want the Vantage specifications sheet and RERA dates in one pack? Ask for the buyer pack.
Frequently asked questions
It should cover a room-by-room snag list and the key papers. Those include the occupancy certificate, possession letter, paid-up receipts and the society handover documents.
Under Section 14(3) of the RERA Act, 2016, the builder must fix defects you report within 5 years of possession. The fix is due within 30 days, at no cost to you.
Section 19(10) of the RERA Act says the buyer must take physical possession within 2 months of the occupancy certificate.
No. The OC shows the local body has cleared the building to live in. Ask to see it before you sign the possession letter.
Plan on 3 to 4 hours for a large 4 BHK. Take a tape, a spirit level, a torch, a phone charger for socket tests and a notebook.